Skip to Content

What’s the Difference Between Design-Build and Design-Bid-Build?

The design-build project delivery method has been used in the U.S. for almost 30 years, but there is still some confusion about what the term really means. The simple explanation is that under a design-build contract, a client hires a design-builder team that will deliver a project through design…

By Carl Kaczmarek

Carl Kaczmarek

The design-build project delivery method has been used in the U.S. for almost 30 years, but there is still some confusion about what the term really means. The simple explanation is that under a design-build contract, a client hires a design-builder team
that will deliver a project through design and construction. In the design-bid-build format, a client hires a team of independent designers to complete the construction plans, then advertises the construction of the project for competitive bid by
interested contractors.

DBB-Blog-1

The Dulles Corridor Metrorail project is an example of a design-build project that we have been working on since 2013. The corridor is expected to be open to the public in 2021.

DBB-Blog-2

The I-95/Telegraph Road interchange project was completed through the traditional design-bid-build process.

Why chose the design-build delivery method?

The most often recognized benefit is time savings. Projects delivered under the design-build method can expect reduction in total design and construction durations by 25 to 50 percent when compared
to similar design-bid-build projects. One of the biggest factors in time savings is the ability for the design-builder to overlap design and construction processes that would normally be completed in stages. An example of the overlapping process occurs
in right-of-way acquisition and utility coordination. For a design-bid-build project, the client needs to complete design, acquire land from property owners, and complete utility relocations before the builder can begin any work. In design-build,
the designer and builder can coordinate right-of-way and utilities while the design is still being developed and utility relocations can occur during the actual construction period.

What are some additional benefits to design-build?

The design-build team is typically selected through a competitive bid process that encourages teams to be innovative and to find cost savings within specific technical requirements.
Since the designer and builder are teamed throughout the entire process, there is also level of communication that does not exist in the design-bid-build method. The builder can review the designer’s construction plans during development to
find constructability issues or find efficiencies that might not be otherwise evident.

What are some risks of design-build?

The primary risk of design-build is that the design-builder becomes wholly responsible to design and construct the project within local, state, and federal requirements. The client will perform preliminary
investigations to reduce some of that risk, but the expectation is once the contract is awarded, the design-builder “owns it all.” On the client’s side of things, there is sometimes the perception that a design-build project may
not actually be more cost effective due to the lack of competitive bidding on a defined product.

Not every project fits the design-build mold, but it is a useful tool that is being used across the country. The success of this method has even created new forms of design-build, such as progressive design-build. Who knows where the industry will take
us next.

About the Author

Carl Kaczmarek

Carl Kaczmarek

Related Insights

Healthcare Construction & Operations News

September 23, 2026

In this article for Healthcare Construction & Operations News, Melissa Covington and Heather Platt, PE, CHC discuss the modernization of Oklahoma State University Medical Center's labor and delivery facilities while maintaining ongoing hospital operations. The authors highlight the planning, collaboration, and innovative design solutions required to upgrade critical healthcare spaces within an existing facility and share key lessons learned for healthcare renovation projects.

Publication

Annandale Pickleball Facility

August 26, 2026

Our firm renovated a former sports center in Annandale, Virginia, into a modern, two-story sports complex with pickleball courts, golf simulators, a fitness center, and other amenities. With these updates, the space once again supports an active lifestyle for the community. We provided full…

Video

Dimensions®

Our annual review and corporate social responsibility report, in one place.