Skip to Content

Colsman Tunnel Rehabilitation

Innovative Trenchless Solution Saving Project Time and Money

The project used an innovative design-build solution to slipline the Colsman Tunnel.

The project used an innovative design-build solution to slipline the Colsman Tunnel.

The fused high-density polyethylene (HDPE) pipe was fed into the tunnel at the western portal, with a machine set up at the eastern portal for the pull-in.

The fused high-density polyethylene (HDPE) pipe was fed into the tunnel at the western portal, with a machine set up at the eastern portal for the pull-in.

The pull head ready to be fused onto the new 48-inch HDPE pipe.

The pull head ready to be fused onto the new 48-inch HDPE pipe.

Client
Garney Construction
Owner
Southgate Water and Sanitation District
Location
Arapahoe County, CO
Markets
Water
Cost
$15 Million
Completed
2020
Region
West

The 7,614-foot-long Colsman Tunnel, located in a suburb south of Denver, Colorado, was a failing tunnel constructed in 1978 that collected and conveyed 100% of Southgate Sanitary District’s 12.4 million gallon per day (MGD) sanitary sewer peak flow. The tunnel had no system redundancy. Based on the tunnel’s age and the continuous wastewater environment, the district became increasingly concerned with the reliability of the tunnel as even partial collapse of the tunnel could result in a significant spill. The district was determined to take a proactive approach to extend the service life of the tunnel by fully rehabilitating or replacing it.

The design-build team of our firm and Garney Construction, with Burns & McDonnell serving as owner’s representative, evaluated project options and sought to minimize the impact on the community, cost, and schedule. We capitalized on a progressive design-build delivery method to slipline the tunnel, saving the district tens of millions of dollars and expediting a potential multi-year timeline, all while maintaining continuous utility service.

Our approach had rarely been used for water and wastewater projects, and never for a project as ambitious as the Colsman Tunnel, which required a nearly 1.5-mile existing tunnel pipeline pull-in. Construction was completed in just six months. The fused high-density polyethylene (HDPE) pipe was fed into the tunnel at the western portal, with a machine set up at the eastern portal for the pull-in. Grouting the annular space between the tunnels was a critical phase of the project, involving a barometric loop to keep the pipeline full and mitigate thermal expansion and pipeline buoyancy. Garney Construction oversaw the drilling of injection points over stretches of 600 feet, up to 90 feet underground, and verified the grout placement with specially built cameras. Together, we addressed many other challenges, including determining the exact geometry of the existing tunnels without reliable records. We also determined pipe loading/stresses with the long HDPE pipeline installed in a 1.5-mile-long tunnel with no intermediate access in live flow.

7,614-foot-long

tunnel

100%

of Southgate Sanitary District’s 12.4 MGD sanitary sewer peak flow

48-inch

high-density polyethylene pipe

Awards

  • 2020 Best Project, Specialty Construction

    ENR Mountain States

  • 2019 Project of the Year Rehabilitation Runner-up

    Trenchless Magazine

  • H20 Award

    Colorado Contractors Association

Related Projects