High Point Regional Health Infrastructure Improvements
Upgrading Campus Systems for Expansion, Efficiency, and Resilience
- Owner/Client
- High Point Regional Health
- Location
- High Point, NC
- Markets
- Health and Wellness
- Square Footage
- 986,000 SF 17,090 SF (central energy plant)
- Cost
- $24.5 million
- Completed
- 2015
- Region
- Southeast
A trusted mechanical, electrical, and plumbing (MEP) engineering partner of High Point Regional Health since 2001, we completed a comprehensive facility assessment of the 748,196-square-foot, 384-bed medical and surgical hospital, 100,150-square-foot cancer center, and 137,640-square-foot cardiac pavilion in 2007. The assessment identified necessary upgrades to chilled water, emergency power generation, and power distribution components, which led directly to High Point Regional Health’s two-year, phased infrastructure improvement plan.
We designed the MEP systems associated with:
- Three new 2,500 kVA emergency generators
- A consolidated electrical service system with 12.5 kV medium voltage distribution
- Three new 1,500-ton high-efficiency chillers and coolers
- An upgraded variable primary chilled water system
- Various steam and chilled water distribution upgrades and expansions
- Several new workshops, offices, and storage facilities
Our MEP professionals also completed preliminary conceptual designs with cost estimates and budget plans.
7,500
kVA of emergency power
12.5
kV campus distribution system
4,500
tons high-efficiency chilling and cooling capacity
Awards
-
2015 Pinnacle Partners in Excellence Award, Best Project $5 Million and Over
Carolinas Associated General Contractors